Tunbridge Wells Wastewater Treatment Works (WTW) Phase 2

Project: Tunbridge Wells Wastewater Treatment Works (WTW) Phase 2 - Civil Engineering Works Client: Costain/MWH Delivery Partnership Location: Tunbridge Wells, Kent

Project Introduction

Coleman Construction & Utilities Limited successfully delivered a complex civil engineering package supporting the major upgrade of Tunbridge Wells Wastewater Treatment Works.

Working on behalf of CMDP JV, the team completed extensive excavation, reinforced concrete works, deep drainage installation, and significant modifications to live operational assets. Through meticulous planning, collaborative working, and coordinated stakeholder engagement, all works were safely delivered within the programme.

Scope of Works

Coleman Construction & Utilities Limited delivered a comprehensive programme of civil engineering works, including: 

All works were undertaken within a live wastewater treatment facility, requiring precise planning to maintain full operational continuity.

Inlet Works Modifications

The inlet works area presented complex engineering and logistical challenges due to restricted access and critical live assets. Elevated winter flows prevented the initial planned cut into the existing channel, requiring resequencing and out‑of‑order working to maintain programme progress.

Key measures implemented included:

Final Settlement Tank (FST) Construction

Construction of the new FST required extensive controlled excavation and careful management of existing assets. Early works included diverting a rising main and installing temporary Legato block walls to ensure protection of adjacent live services.

Key construction stages included:

Following construction, the tank underwent and passed full hydrostatic testing, enabling commissioning in line with programme requirements.

Pipework Installation

Pipework for feed and desludge systems was connected to infrastructure previously installed for future expansion. Temporary works were deployed throughout, including sheet and frame systems, with vacuum excavation used to safely manage interfaces with existing services.

Highlights included:

Ductwork Installation

Site‑wide ducting was installed using 150mm twin‑wall ducting, complemented by Cubis RapidStak draw pits. This new infrastructure supports ongoing and future electrical and controls upgrades across the treatment works.

Challenges and Solutions

This project demanded innovative engineering, safe systems of work, and adaptive planning. The Coleman team successfully addressed multiple constraints through:

All pipework was fully tested using water‑drop methods prior to commissioning, and deep excavation activities were completed with zero incidents, highlighting the effectiveness of the project’s safety culture.

Project Outcomes and Benefits

The successful delivery of the Tunbridge Wells WTW upgrade reflects Coleman Construction & Utilities Limited’s capability to execute technically demanding civil engineering works within live operational environments.

Key outcomes include:

Share: