Lingfield WwTW Civil Engineering

Project: Lingfield WwTW Civil Engineering Client: Costain/MWH Delivery Partnership Location: Lingfield, Surrey

Project Introduction
Coleman Construction & Utilities Limited has successfully delivered a major 70-week civil engineering wastewater treatment works sub-contract for Principal Contractor CMDP JV, on behalf of Southern Water in Lingfield, Surrey, at £3.6m, its largest value contract to date.

As part of the AMP capital investment programme, Southern Water had identified the need for Phosphorus removal (regulatory date 22 December 2024): Lingfield WwTW was already required to achieve P removal, however, a more stringent permit was introduced at the site this AMP Control Period, with new assets required to meet the revised permit conditions. In addition to this, the project was to implement improvements at the site to facilitate an increase of the full flow to treatment (FFT) from 83 l/s to 127 l/s, which involved the installation of new process assets to provide additional biological treatment capacity and accommodate projected population growth to 13,390 of Lingfield and its surrounding villages at the design horizon of 2035.

The works comprised therefore, of an upgrade to the existing 30m3 Ferric Dosing Facility, a new Tertiary Treatment Plant, converting/upgrading the existing Pumping Station, upgrading the Sewage Pumps, a new 12.5m diameter Radial Settlement Tank, a new 31m diameter Trickling Filter, new cross site pipework and ductwork installations and an upgrade to the site power supplies and telemetry to meet the Environment Agency and Wtaer Industry National Environment Programme requirements.

Coleman Construction & Utilities Limited’s contracted civil engineering scope comprised bulk excavation, new chambers, pipework, drainage and manholes, extension of a roadway and provision of hardstanding’s, site wide ducting, draw pits and new reinforced concrete structures.

The contract was underpinned throughout by a collaborative approach with CMDP JV and Southern Water, as well as other project stakeholders, providing the basis for proactive communication and highly coordinated activities, resulting in the safe and successful completion of this Wastewater civil engineering project.

Project Deliverables – Civil Engineering Scope
Trickle filter:

Humus tank:
Particularly challenging due to existing pipework diversions and existing concrete structures needing to be broken out. Groundwater managed using 6” hydraulic pumps filtered through a silt buster.

MCC x 2:

Caustic dosing area:

Tertiary Area:

Generator Area:

Tertiary pump station:

Ductwork:
Challenging due to 140No plus existing underground services avoided many of which unknown.

Pipework:
Very challenging due to many underground services needing to be avoided.

Challenges and Solutions
Several challenges have been met throughout the project by Coleman Construction & Utilities Limited, which are detailed below:

Benefits

Share: