Phase 2 of our Tunbridge Wells South Wastewater Civils project for Southern Water on behalf of valued PC CMDP – JV is progressing nicely. Our Senior Site Manager Keith Sturmer and our civil engineering trades have completed the following works recently to meet the project milestones. Much of the work has been under SCO:

FST
> Completed the TW Designed mat for the piling rig in time for piling
> Diverted the rising main under SCO from the FST footprint.

Inlet works
> Reducing the excavations for the new flowmeter and diversion chambers.
> Diverting wash water and liquor return pipes under SCO.

RAS area
> Excavation and installation of 250mm Ductile iron pipe and associated ductwork.
> Concrete base constructed for the flow meter.

Thanks to the entire team including supply chain partners and Coleman Plant Hire Ltd for your collaboration and safe delivery in challenging circumstances.