Hailsham South Wastewater Civils June 2021 Progress Update

June 2021 has seen Coleman Construction & Utilities Limited move nearer to practical completion of its wastewater civil engineering contract at Southern Water’s Hailsham South site.

Working in close collaboration with Principal Contractor CMDP, the Coleman team have continued to deliver construction techniques that solve environmentally sensitive project requirements in a safe and sustainable manner.

Our specialist teams have been delivering extensive below ground pipeline and sewer solutions for this project, undertaking enabling works, groundworks, temporary works and permanent works to improve the quality of final effluent that is being discharged from the works and entering the local water course’s and to meet the regulatory output dates set by the Environment Agency.

Progress for June 2021 has included:

Secondary Ferric Dosing

Oxidation ditch pipe work

Lagoon landscaping and pond construction

Fuel delivery area

Coleman Construction & Utilities Limited provide a fully managed civil engineering service offering for the water sector. We employ resources specifically trained to work on both clean and dirty water sites. All clean water operatives carry EUSR cards and our entire workforce is fully accredited for the tasks they undertake and the plant that they operate.